Final Totals for Sewer Overflows from Historic July Rainfalls

Tuesday Aug 7th, 2018

Green banner with DPW logo and text "Department of Public Works Press Release"

Final reports are in for sewer/stormwater overflows that occurred during the last weeks of July.  These resulted from the heaviest rainfall in Baltimore in July on record.  Much of this overflow was released through structured outfalls, designed as part of Baltimore’s sewer system more than 100 years ago. The City will close the last of these structures once the new Headworks project is operational at Back River in late 2020. This will also eliminate over 80 % of such overflows into our streams and harbor. Headworks is part of the City’s $2 billion wastewater Consent Decree program.

To recap, from July 21-25 – 45 million gallons were released. This was already reported.  On July 27 an additional total of approximately 3.15 million gallons was released from eight locations.

Last week DPW also reported on storm damage to sewer lines at two locations: Maidens Choice Run (behind the 300 block of S. Beechfield Avenue), and on the Gwynns Falls near Edmondson Avenue and Hilton Parkway. Severe structural damage caused sewage/rainwater releases that were stopped by bypass pumping on August 1 (Maidens Choice Run) and on August 4 (Gwynns Falls). These overflows were 1.3 million gallons (Maidens Choice Run), and 36 million gallons (Gwynns Falls).  Repair work is pending. 

The Baltimore City Health Department and the Maryland Department of the Environment were notified of the sewage releases. The public is reminded to avoid contact with urban waterways due to the risk of pollution. For information about health concerns as a result of sewer overflows please go to http://health.baltimorecity.gov/sanitary-sewer-overflows-sso.

As a reminder, citizens who experience basement sewage backups as a result of rain events are encouraged to take advantage of the city’s Expedited Reimbursement Program (ERP).  This program is to reimburse residents and property owners for cleanup costs related to sewage backups caused by wet weather.  Application and eligibility information can be found at this link: https://publicworks.baltimorecity.gov/sewer-consent-decree/building-backups. Please note that this program is NOT designed for costs related to flood damage, hurricanes, or other extreme weather events.

Related Stories

DPW Offices, Sanitation Yards Closed on Juneteenth, Monday June 19

Baltimore City Department of Public Works (DPW) Director Jason W. Mitchell reminds residents that Juneteenth is Monday, June 19, 2023, and is a City holiday. DPW offices and sanitation yards will be CLOSED.

Weekly trash and recycling collections are NOT impacted by the Juneteenth closure. Monday is not a scheduled curbside trash or recycling collection day.

DPW Extends Deadline to Receive Discount for Paperless Billing Sign Up

The Baltimore City Department of Public Works (DPW) is pleased to announce that Baltimore City residential water customers have more time to sign up for Paperless Billing and receive a one-time, 5% discount off a monthly water bill. Residents who enroll in paperless billing by Friday, June 30, will receive the 5% discount.

DPW Offices, Sanitation Yards Closed Memorial Day: Monday, May 29

Baltimore City Department of Public Works (DPW) Director Jason W. Mitchell reminds residents that Memorial Day is on Monday, May 29, 2023, and is a City-observed holiday. DPW offices and sanitation yards will be CLOSED.

Contact

James E. Bentley II
410-545-6541
Jennifer Combs
410-545-6541
After hours, weekends, or holidays please call 410-396-3100 for the duty officer

The Baltimore City Department of Public Works supports the health, environment, and economy of our City and region by cleaning our neighborhoods and waterways and providing its customers with safe drinking water and sustainable energy practices.