Increased Traffic Flow Continues at Howard/Pratt Street Worksite

Thursday Aug 15th, 2019

Green banner with DPW logo and text "Department of Public Works Press Release"

Traffic is fully restored along Pratt Street, and two northbound and two southbound lanes on Howard Street are now open, marking the progress that the Baltimore City Department of Public Works (DPW) and its partners are making on the intersection’s complex infrastructure repairs.  

These roadway openings signal that DPW is nearing the end of its sewer, storm drain, and water main repairs. This week Maryland Transit Administration (MTA) has been working to restore its Light Rail infrastructure, which was damaged when underground infrastructure at the location failed on July 8.

DPW is leading a multi-agency team that includes local, state, and private interests. In collaboration with MTA and CSX, DPW oversaw the design and construction of the support system to shore up and protect the underground portion of the work site. The Baltimore City Department of Transportation (DOT) is coordinating the design for the conduit replacement, and the Maryland Transit Administration (MTA) is protecting its Light Rail assets and making sure a handicap access ramp is rebuilt. Daily meetings were being coordinated by the City’s Office of Emergency Management, but have been suspended since most of the work has been completed.

DPW’s Office of Engineering and Construction has accelerated the repair process by using in-house talent to design the water main replacement work. Utilization of the design/build method avoids delays as the site is prepped.  This more efficient process is in line with the vision brought to the agency by DPW Director Rudolph S. Chow, P.E.

Director Chow extends his gratitude to City residents, commuters, businesses, and visitors for their patience while the inter-agency teams worked to pursue a long-term fix.

Related Stories

DPW Offices, Sanitation Yards Closed on Juneteenth, Monday June 19

Baltimore City Department of Public Works (DPW) Director Jason W. Mitchell reminds residents that Juneteenth is Monday, June 19, 2023, and is a City holiday. DPW offices and sanitation yards will be CLOSED.

Weekly trash and recycling collections are NOT impacted by the Juneteenth closure. Monday is not a scheduled curbside trash or recycling collection day.

DPW Extends Deadline to Receive Discount for Paperless Billing Sign Up

The Baltimore City Department of Public Works (DPW) is pleased to announce that Baltimore City residential water customers have more time to sign up for Paperless Billing and receive a one-time, 5% discount off a monthly water bill. Residents who enroll in paperless billing by Friday, June 30, will receive the 5% discount.

DPW Offices, Sanitation Yards Closed Memorial Day: Monday, May 29

Baltimore City Department of Public Works (DPW) Director Jason W. Mitchell reminds residents that Memorial Day is on Monday, May 29, 2023, and is a City-observed holiday. DPW offices and sanitation yards will be CLOSED.

Contact

James E. Bentley II
410-545-6541
Jennifer Combs
410-545-6541
After hours, weekends, or holidays please call 410-396-3100 for the duty officer

The Baltimore City Department of Public Works supports the health, environment, and economy of our City and region by cleaning our neighborhoods and waterways and providing its customers with safe drinking water and sustainable energy practices.