Back River Project Moves Forward With New Construction Model

Wednesday May 4th, 2016

Green banner with DPW logo and text "Department of Public Works Press Release"

The Baltimore City Board of Estimates approved a contract Wednesday, May 4, that will allow work on the Headworks project at the Back River Wastewater Treatment Plant to proceed under an innovative, cost-saving model known as Construction Manager at Risk (CMAR).

The Headworks project is needed to alleviate a hydraulic restriction that keeps sewer water from efficiently entering the treatment plant. It causes a 10-mile-long backup in the sewer system that contributes to sewer overflows in the City, particularly following hard rains.

The Baltimore City Department of Public Works (DPW) turned to the CMAR model last year after bids to build the massive Headworks project ran more than $100 million over the estimated cost.

DPW officials are exploring the use of the CMAR model for other large infrastructure projects.

“I’m optimistic that by thinking creatively we will be able to deliver some of our projects for less money and in less time than what has become typical,” said DPW Director Rudy S. Chow, P.E. “We have billions of dollars in capital projects ahead of us, and we must continue to invest our ratepayers’ money wisely.”

A joint venture team of Clark Construction and Ulliman Schutte, LLC, won a contract for $3,839,000 to perform pre-construction services on the Back River project. The team was one of four that submitted proposals and were interviewed by members of DPW’s Office of Engineering and Construction. The Clark/Ulliman Schutte team was also approved by the Office of Boards and Commissions and the Architectural and Engineering Awards Commission.

The pre-construction process establishes the best way to perform what will be a multi-year build costing hundreds of millions of dollars. A guaranteed maximum price is also established in this early process in order to avoid cost overruns, and provides DPW with significant control over the process. The overall project schedule and cost is expected to be much less than with other construction models.

It is likely, under terms of the agreement, that the Clark/Ullimann Schutte joint venture will also be selected to perform the construction.

The Headworks project should be ready to move to construction by early next year. It is expected to be completed by the end of 2020.

Related Stories

DPW Offices, Sanitation Yards Closed on Juneteenth, Monday June 19

Baltimore City Department of Public Works (DPW) Director Jason W. Mitchell reminds residents that Juneteenth is Monday, June 19, 2023, and is a City holiday. DPW offices and sanitation yards will be CLOSED.

Weekly trash and recycling collections are NOT impacted by the Juneteenth closure. Monday is not a scheduled curbside trash or recycling collection day.

DPW Extends Deadline to Receive Discount for Paperless Billing Sign Up

The Baltimore City Department of Public Works (DPW) is pleased to announce that Baltimore City residential water customers have more time to sign up for Paperless Billing and receive a one-time, 5% discount off a monthly water bill. Residents who enroll in paperless billing by Friday, June 30, will receive the 5% discount.

DPW Offices, Sanitation Yards Closed Memorial Day: Monday, May 29

Baltimore City Department of Public Works (DPW) Director Jason W. Mitchell reminds residents that Memorial Day is on Monday, May 29, 2023, and is a City-observed holiday. DPW offices and sanitation yards will be CLOSED.

Contact

James E. Bentley II
410-545-6541
Jennifer Combs
410-545-6541
After hours, weekends, or holidays please call 410-396-3100 for the duty officer

The Baltimore City Department of Public Works supports the health, environment, and economy of our City and region by cleaning our neighborhoods and waterways and providing its customers with safe drinking water and sustainable energy practices.